Dilip Buildcon Ltd restrained by NHAI from participating in bids

Published

on

Dilip Buildcon Ltd restrained by NHAI from participating in bids

Dilip Buildcon Ltd. through its SPV i.e. DBL Anandapuram Anakapalli Highways Ltd., (hereinafter retbrred to as “Concessionaire”) was undenaking the development, maintenance, and management of National Highway No. 05 (New NH-16) Anandpuram – Pendurthi – Anakapalli including the section from km 681.000 to km 731.780 (approx. 50.780 km).

While the Concessionaire was carrying out the work at the said Project by following all the specifications and standards in accordance with the provisions of the Concession Agreement and other standard industry practices, on 06.07.2021 , at around 5:50 PM, two (02) Girders of span length of 4l m on LHS (G1 & G2 of span A1-A2) for construction of flyover at Ch. 730+819 located at the said Project toppled and fell on two vehicles plying underneath and causing casualties at the said site of the Project. The Concessionaire on being informed of the said accident, at the very outset instructed its employees located at the site to safely rescue the passer-by’s and fully cooperate with the investigating authorities. The Concessionaire has also duly compensated the families of the deceased persons and persons who have suffered injuries due to the said accidcnt.

Thereafter the Concessionaire duly informed the Authority of the accident at the said Project, and the Authority thereafter constituted an expert committee to investigate the incident and submit its report of the cause and to ascertain to reason of failure leasing to the said incident. The report from the expert committee is still awaited which is anticipated to be prepared by the committee in approximately coming 2-3 weeks, however till then the Authority through its interim order bearing Ref. No. NHAI/Tech/AP/APA/COC /2021 (E-91822)1906 dated 12.07.2021, has temporarily restrained the Concessionaire and Dilip Buildcon Ltd. (as being Promoter of Concessionaire) and other promoter(s) of the Concessionaire from participating in any NHAI / Authority’s bids directly or in association JV) with immediate effect until further order / decision on the findings of the investigation after following due procedure.

News Source : IIFL

Advertisement
Continue Reading

Construction Infrastructure

The Adani Enterprises unit has received a letter of approval for an NH project in Maharashtra

Published

on

The Adani Enterprises unit has received a letter of approval for an NH project in Maharashtra

Adani Road Transport Ltd (ARTL), a wholly owned subsidiary of Adani Enterprises, has received LoA for a project involving six laning of Kagal-Satara section of NH-48 (old NH4) in Maharashtra. The project will be executed under the Bharatmala Pariyojana at ₹2,008.47 crores. The construction period for the 67-km long road project is expected to be 2 years from the date of appointment and the concession period will be 18 years.

With this project award, Adani’s road portfolio will have total 14 projects with more than 5,000 lane km with asset value exceeding ₹41,000 crore spread across India.

Continue Reading
Anyskill-ads

Facebook

Trending