Connect with us

Construction Infrastructure

Terex MPS Plant Chosen for Laos Dam Project

Published

on

Terex MPS Plant Chosen for Laos Dam Project

The dam, which is 105m high and 700m long at the top, will produce electricity in three groups: two units of 250 MW to be distributed in Thailand, and one group of 150 MW to be distributed for local use in Laos. The solution consisted of a complete crushing plant to produce 1,500mtph of concrete aggregates. The plant is made up of two Simplicity Vibrating Grizzly Feeder 5220, two Cedarapids Jaw Crushers JS4552, four cone crushers, of which two are Cedarapids MVP550X and the other two are Cedarapids MVP450X, three Vertical Shaft Impactors, two Cedarapids Horizontal Screens TSV6202, and six Cedarapids Horizontal Screens TSV8203. Additionally, the set up includes an impressive 45 conveyors (total length of 1,400m), and the installation of 5,000kW of power.

The plant is being fed by blasted sandstone rock with a high abrasion index to produce 0/5, 5/12, 12/25 and 25/50 mm, as dictated by the mix design of the RCC, with any excess being recycled. A reclaiming plant transports aggregates from stock to a cooling plant via two downhill conveyors (one for coarse aggregates with a capacity of 1,800mtph and one for sand with a capacity of 700mtph). The supply is completed by a set of conveyors with a capacity of 1,000cmh to pour RCC into the dam. Due to the abrasiveness of the sandstone, distributor ICM srl, Italy, designed the plant to use jaw crushers and cone crushers in the first instance to get the rock to the required size for the RCC—at this stage not worrying about the shape of the aggregate.

Once sized, the shape is improved using the Vertical Shaft Impactors. Mr. Icilio Guicciardi, ICM explains, “This is a philosophy that always gives good results in terms of the quality of the aggregates and the reduction of wear costs. Having a solution that satisfies our customer’s strict requirements was of utmost importance to us and we knew that this plant set up would produce the output required.” Commissioned in 2018, the plant was supplied by distributor ICM srl, Italy, who also completed all the engineering required (except civil works), equipment, electrical system (power and controls), steel work (hot galvanized), delivery, assistance to assembly and erection up to commissioning (with customer crew). The plant is now being operated by Sinohydro, with works expected to be completed in 2023.

News Source : CWGRP

Advertisement
Continue Reading

Construction Infrastructure

The Adani Enterprises unit has received a letter of approval for an NH project in Maharashtra

Published

on

The Adani Enterprises unit has received a letter of approval for an NH project in Maharashtra

Adani Road Transport Ltd (ARTL), a wholly owned subsidiary of Adani Enterprises, has received LoA for a project involving six laning of Kagal-Satara section of NH-48 (old NH4) in Maharashtra. The project will be executed under the Bharatmala Pariyojana at ₹2,008.47 crores. The construction period for the 67-km long road project is expected to be 2 years from the date of appointment and the concession period will be 18 years.

With this project award, Adani’s road portfolio will have total 14 projects with more than 5,000 lane km with asset value exceeding ₹41,000 crore spread across India.

Continue Reading
Anyskill-ads

Facebook

Trending